Deployed references, with the numbers left in
Data hall operators rarely let suppliers publish their names, and we do not ask. What we can publish is what the projects were asked to do and what changed afterwards — rack counts, lead times, power envelopes and measured PUE. The three references below are reported the way our clients review them internally: industry, requirement, solution, result. Across the export record the line has shipped to data halls in 12 countries, including programs in North America, Southeast Asia, the Middle East and Africa.
Request a Quotation Read the Deployments
45+ data halls · 12 export countries · results reported as measured, not modeled
24 racks, liquid and busbar, set in 6 weeks
An AI infrastructure operator was fitting out a 24-rack training hall against a fixed launch date, with cabinets in the 40–132 kW class that could not wait for follow-on site integration crews. The building had power and cooling plant ready — what it did not have was three weeks of slack for after-delivery assembly.
- Solution: liquid-cooling ready GPU frames with manifolds factory-held at 1.5× working pressure for 24 hours, zero drop, and busbar-slot columns so tap-off boxes landed on set positions.
- Alignment: 800 × 1200 mm frames checked against the NVL72-class footprint at the punching stage, not on the floor.
- Result: all 24 racks delivered, set and connected in 6 weeks from drawing sign-off — the row powered without a single field-drilled column.
12 aisles closed, PUE 1.55 → 1.32, zero downtime
A regional colocation provider was carrying a measured PUE of 1.55 across a live multi-tenant hall and had committed to an efficiency target that open aisles could not reach. The constraint was operational: 12 aisles serving paying tenants, with no maintenance window longer than a shift.
- Solution: 12 mm tempered glass containment doors, fixed and drop-away roof panels, and brush-sealed blanking panels — retrofitted one aisle at a time inside tenant maintenance windows.
- Fire path: drop-away roof panels release below 72°C and link to the hall's FA system, keeping the sprinkler plan intact under containment.
- Result: measured PUE settled at 1.32 over the following quarter, with zero tenant downtime across all 12 aisle closures.
8 unattended sites, 18U–42U, in two waves
An edge integrator was rolling out 8 micro-sites — retail back-rooms and telecom shelters — where floorspace is measured in square meters, ambient follows ASHRAE A3/A4 envelopes, and no technician is stationed on site. Full-size 42U halls were never the answer; repeatable small frames that ship flat were.
- Solution: compact 18U–42U frames with locking doors, brush-sealed cable entries and wide-temperature-ready builds for unattended A3/A4 environments.
- Logistics: CKD flat-pack packing cut shipped volume by around 40%, letting one consignment cover multiple sites per wave.
- Result: 8 sites commissioned from two shipping waves on a 30-day production lead, with a common spare-parts list across the whole estate.
Your hall can be the next number on this page
References verified by request · 30-day FOB lead · MOQ 5, samples in 15 days