Design guide 03

A containment works at six nodes. The panels are only one of them.

Six construction nodes decide whether an aisle is actually closed. Get any one of them wrong and the containment looks finished while the air keeps escaping.

3 to 8 Cabinets in one sealed run, extendable
2–3 weeks On site, survey to handover
4 pages Containment test report, third-party

Definition

What is enclosed, and what is not.

What is enclosedthe volume in front of the equipment intakes, between two facing rows

What seals itthe end doors, the roof panels, and the seals along the cabinets

What it is notnot a sealed room, not a fire compartment, not a pressure vessel

The aisle is a controlled volume, not an airtight box. Everything here is about which openings are deliberate and which ones are simply left over from installation.

Node map

Where the six nodes sit.

Cross-section of a sealed cold aisle with the six construction nodes N1 to N6 marked: row layout, door type, door frame width, door leaf, roof panel and roof panel support HOT AISLE HOT AISLE COLD AISLE N5 roof panel N6 roof support N2 door type N3 frame width N4 door leaf N1 row layout The six nodes are the six places where the volume is closed, or is not. Dashed: the end door, standing beyond this cut.
N1 row layout · N2 door type · N3 door frame width · N4 door leaf · N5 roof panel · N6 roof panel support.
N1

Row layout

  • Two rows, facing

    Two rows facing each other, intakes to the aisle.

  • Row length

    Row length from 3 to 8 cabinets, extendable.

  • Aisle width

    Aisle width is set by what has to pass through it.

Confirm Measure the clear passage you need — a loaded trolley, a person carrying a chassis — before the frame is ordered.

Common error Fixing the aisle width from a drawing instead of from the trolley.

N2

Door type

End door type
Door typeClear openingFloor obstructionTrolley accessSpace needed at the row end
Dual sliding widest of the three, both leaves move none — the leaves run along the frame best: the full opening stays clear frame wider than the opening it serves
Single sliding one leaf, roughly half the frame none good, if the clear opening is measured first same frame rule, one leaf to park
Single hinged the full leaf width, in one plane the swing arc, kept clear at all times workable, but the arc has to stay empty swing radius in front of the row end

Confirm Choose the door from the trolley that has to pass through it, not from the drawing that shows it.

N3

Door frame width

Frame width > 2 × required clear opening
  • A sliding leaf parks in front of the frame, so the frame has to be wider than the opening it serves.
  • Order the frame after the clear opening is agreed, not before.

Common error Ordering the frame first and discovering the trolley does not fit.

N4

Door leaf

  • Construction

    Tempered glass in an aluminium frame.

  • Visibility

    Visibility into the aisle from the corridor, without opening anything.

  • Operation

    A sliding leaf closes again with one hand.

Rule A door that has to be held open is a door that stays open.

Common error Treating the end door as a decoration and leaving it propped open.

N5

Roof panel

What it doescloses the top of the aisle, so return air cannot spill over the row

How it opensthe panel flips open

Why that mattersthe open panel is the path by which a gaseous suppression agent enters the aisle volume, and by which smoke leaves it

Confirm Confirm the direction of opening and the clearance above with your fire system contractor before the frame is fixed.

Details

The two nodes that carry the rules.

Two details: the end door seen from the aisle with the leaves parked in front of the frame, and a section through the roof panel showing its lap and opening direction END DOOR, VIEWED FROM THE AISLE leaf, parked leaf, parked leaf, closed position clear opening frame width — more than twice the clear opening Sliding leaves park in front of the frame, so the frame is wider than the opening it serves. Frame fixings shown at both posts. ROOF PANEL SECTION clearance above roof panel, closed open position lap over the cabinet top cabinet top, in section hinge The open panel is the path by which a gaseous suppression agent enters the aisle volume. Confirm the opening direction and the clearance above before the frame is fixed.
End door viewed from the aisle: the leaves park in front of the frame · frame fixings at both posts · roof panel lap over the cabinet tops · opening direction and clearance above.
N6

Roof panel support

Support condition
Support conditionWhat it rests onChoose whenWhat to check
Freestanding its own frame, down to the floor the cabinets are not to carry the panel, or the row may change later footprint at the row end, and that nothing is drilled into the cabinets
Rack-supported the cabinet tops the row is fixed and the cabinets are level that the cabinets are rated to carry it, and that the row is genuinely level
Suspended the structure above the ceiling can take it and the height above is fixed what else hangs up there, and the clearance for the opening panel

In an existing row, cabinets are rarely all the same height: the panel and the cabinet together have to hold one constant height along the run.

Common error Assuming the row is level because the drawing says it is.

Prerequisites

What the cabinets have to do first.

  • Front door mesh at 75% or above; rear door mesh at 60% or above
  • One 1U blanking panel per unused U
  • Gaps between adjacent cabinets sealed, not left to the trim
  • Both row ends closed, including the space above and below the cabinets
  • Cabinets level and coupled to each other, so the run holds one height

Rule Containment does not fix a cabinet that was not ready for it.

Retrofit

Look above the row before anything is ordered.

  • Cable trays

    depth, and whether they pass over the aisle

  • Light fittings

    position and how they are serviced

  • Pipework

    routing and any valves that have to stay reachable

  • Sprinkler heads

    position, and the plane they sit in

  • Structure beams

    clearance for the roof panel and its opening swing

  • Columns

    whether the row has to stop short

Rule Anything that would sit inside the containment volume is a change to the design, not a site cut.

Delivery

The steps on site, and what the row can grow into.

  1. 01Survey the row and the space above it.
  2. 02Fix the frame and the door frames to the agreed clear opening.
  3. 03Level and couple the cabinets.
  4. 04Fit the roof panels, then the end doors.
  5. 05Seal the row ends and the gaps between cabinets.
  6. 06Commission and hand over with the measured numbers.
3 to 8 cabinets
  • Extendable: the aisle grows with the row.
  • 2–3 weeks on site, survey to handover.
  • Roof panels and end doors come off again for the next section.

Rule Extend the row later without rebuilding the aisle.

Handover

A containment is commissioned, not just installed.

  1. 01Check every seal: row ends, cabinet gaps, cable cutouts.
  2. 02Operate both end doors through a full cycle and confirm they close on their own.
  3. 03Operate each roof panel through its full opening and confirm the clearance above.
  4. 04Measure intake temperature at the bottom, middle and top of one rack, then compare against the room.
  5. 05Record the baseline and hand it over with the drawings and the test report.

Cold aisle containment test report — 4 pages

Specification block

Copy this into your technical requirement.

Containment: sealed cold aisle between two facing rows, 3 to 8 cabinets, extendable End door: sliding, tempered glass leaf in an aluminium frame; frame width > 2 x clear opening Roof panel: closes the aisle top; flips open for suppression access Roof panel support: freestanding / rack-supported / suspended - state which on the drawing Cabinet prerequisites: front mesh >= 75%, rear mesh >= 60%, blanking panels, row ends sealed Handover: measured intake temperatures, door and roof panel operation, containment test report